Four New Contracts Signed in Sweden

19.03.2026.

Four new contracts have been signed with the Swedish transmission system operator Svenska kraftnät for the design of 400 kV transmission lines in Sweden, with a total length of nearly 600 km.

The projects, with a total value of approximately EUR 30 million, will be delivered in partnership with Tyréns, with Dalekovod-Projekt acting as the lead partner. These large-scale infrastructure projects include feasibility studies, conceptual and detailed design, technical support during construction, and preparation of as-built documentation.

Projects:

- Stora Luleälven – design of two new 400 kV transmission lines (10 km + 24 km). The preparation of design documentation is planned until December 2028, while project completion is expected in 2033.

- Hall–Hedenlunda – a new 400 kV transmission line with a total length of 77 km. The preparation of design documentation is planned until July 2030, with project completion expected by 2034.

- Njutånger–Mehedeby – two partially parallel 400 kV transmission lines, each approximately 150 km long. The preparation of design documentation is planned until March 2029, with project completion expected in April 2034.

- Skåne Syd – three new 400 kV transmission lines (17 km + 70 km + 75 km). The preparation of design documentation is planned until March 2034, while project completion is expected in the period from 2036 to 2038.

These projects further strengthen the position of Dalekovod-Projekt and the Dalekovod Group in the Scandinavian market and represent a continuation of successful cooperation with Svenska kraftnät in the development of key energy infrastructure.

At the same time, Dalekovod-Projekt’s strong presence in the Scandinavian market enables continuous and stable company growth, while the newly awarded projects will support the further expansion of its engineering team.